Friday, 8 March 2013

Liberal Party transport plans

Having already done the Labor transport plan (Metronet), I'm going to present the Liberals public transport plan.
They plan to -

MAX Light Rail map
- Build the MAX light rail project, with lines going to Balga Polytechnic via Alexander Dr and Mirrabooka (the first line to be built), Victoria Park via Hay St, and QEII Medical Centre, for $1.8 billion
- Build an Airport Rail Link with stations at the Domestic and International Terminals, and Forrestfield, for $1.9 billion
- Provide free off-peak public transport to carers at a cost of $1.2million (an extension of the free seniors public transport)
- Build a 560-bay multi-storey carpark at Edgewater Train station, for $47 million
Airport Rail Link

OPINION
GOOD
LIGHT RAIL
I also think the light rail is a good idea. The Alexander Dr corridor is far from heavy rail lines, and Mirrabooka is a major regional centre. The route to Victoria Park currently is the busiest bus corridor in Perth (albeit via St Georges Tce), and QEII is also an important centre.
Light rail is much cheaper than heavy rail in those corridor (since there is no reserved right-of-way, heavy rail would almost certainly be in tunnel, as elevated rail would be very unpopular), and can be a good selling point. It can bring people to Perth, and like Metronet, improve property values in areas such as Mirrabooka.
AIRPORT RAIL LINK
Most big cities have airport rail. Airport rail will help bring Perth into the big-city league, and make transport easier for residents of Perth taking a plane, tourists, business travellers and residents of Forrestfield and the general Foothills area. It will increase Perth's profile.
CARPARK
A multi-storey parking garage at Edgewater will help relieve parking pressures, while not taking up too much space. Edgewater is a good spot as it lacks feeder buses, increasing the need for parking.
BAD
LIGHT RAIL
Since the Victoria Park route is busiest, it should go ahead before Mirrabooka.
AIRPORT RAIL LINK
On the other hand, airport rail links are expensive, and some people believe they should not take funding from other, more useful public transport, just to join an abstract 'big-city league'.
CARPARK
As I've said before, excessive station parking is a problem. It is expensive to provide (especially in multi-storey form), takes up space (although to a lesser degree in multi-storey form), and makes walking to stations difficult and undesirable. If the problem is that Edgewater has no feeder buses, they can be provided for less than extra parking.
COSTING
The total cost of these promises will be about $3.75 billion. Let's see what costing we will come up with ourselves.

Light rail - 22km
Surface heavy rail - 4 km
Underground heavy rail 4km

Using figures explained in the previous, Metronet, post, as well as $20 million per km for  light rail, this will come to -
$20 (22) + $25 (3) + $250 (5) + $47 +1.2   million
$440 + $75 + 1250 + 47 +1.2
= $1814.2 million or $1.8 billion

This is less than half the official costing! You could nearly build both this and Metronet for the $4.4 billion or so Treasury said just Metronet would cost. While contingencies are necessary, this needs to be within reason, and I think that the total cost of Liberal public transport should not exceed $2 billion.

Labor Metronet review

With the state election fast approaching, Labor has put forward its plans for public transport. These are packaged under the term Metronet. This involves the construction of several heavy rail lines.

PLANNED LINES



The Northern Circle Line (NCL) will run over a new railway along Reid and Tonkin Hwys, as well as employing existing tracks along the Joondalup (to Stirling) and Midland (to Bayswater) lines to form a loop. New stations will be at Balcatta (Erindale Rd presumably), Wanneroo Rd, Mirrabooka Av, Alexander Dr, Noranda (Benara Rd presumably) and Walter Rd.
A line will also be constructed to Ellenbrook, which will branch off the NCL after Noranda, with stops at Bennett Springs (probably the intersection of Reid Hwy and Beechboro Rd), Whiteman Park and Ellenbrook.
The map also shows a line to Wanneroo, but this is not mentioned in text. I don't know of any good rail corridor to Wanneroo, and money for a tunnel would better be spent in more inner areas.
The Southern Circle Line (SCL)will incorporate an airport line previously proposed by the Liberals (from Bayswater to Forrestfield), as well as electrification and amplification of a freight line for passenger service from Forrestfield to Fremantle. New station will be at Airport West (near the current domestic terminal site, with domestic to be consolidated at the international terminal and the site redeveloped as a business park, AFAIK), Perth Airport, Forrestfield, Wattle Grove, Kenwick Junction (interchange with Armadale Line), Thornlie, Nicholson Rd, Ranford Rd, South Lake (interchange with Mandurah Line), Yangebup and Coogee, then looping back using the existing Fremantle Line tracks, through the city to the Midland Line, to Bayswater.
A dedicated airport line will also be built paralleling the SCL between Forrestfield and Shenton Park, perhaps with specialised rolling stock.
The Joondalup Line will be extended from Clarkson to Yanchep, and the Armadale Line to Byford (although the map shows a line all the way to Pinjarra!)

OPINION

GOOD

SUBURBAN RAIL

This plan focuses on delivering more cross-suburban rail, an very good idea. According to the Public Transport for Perth in 2031 plan, the inner city (CBD, West Perth, East Perth, Northbridge) only accounts for 18% of jobs in the metropolitan area (see page 12). This is only set to increase, as congestion in the CBD and plans such as the Stirling City Centre and Murdoch Mix draw more employers into secondary CBDs. Metronet will add Kewdale (the 2nd largest employment area), Canning Vale (7th largest), Malaga (10th), Balcatta (11th), This is more efficient, as instead of having full trains heading into the city in the morning, but near-empty trains heading out, those empty trains will have more passengers on them, which is better for the environment and for the cost recovery of public transport.

SOCIAL

Rail will be delivered to neglected corners of suburbia, affording better access to amenities in the CBD and along existing railway lines (eg. shopping, universities, employment), and perhaps spawning new amenities to these places, drawn by rail access. This will help combat issues such as youth unemployment and unrest.

FINANCIAL

As the plan consists of surface heavy rail, it is much cheaper than tunnelled alternatives, while still offering the speed and capacity of heavy rail. Greater accessibility, as alluded to above, would bring greater investment, as a result of higher land value, and increase access to high paying jobs, which are concentrated in the CBD.

BAD

TRACK CAPACITY

However, there is a disturbing number of lines converging on the Midland Line (five, six if you count the phantom Wanneroo line;). With regular 20 tph signalling, the maximum frequency for each line during peak hour is 4 tph, or every 15 minutes, what is being run in the off-peak. An upgrade to 30tph signalling could see 6tph, but this is what the overcrowded Midland Line receives during peak hour currently, leaving little room for growth other than traffic from Perth to before Bayswater being put onto the other lines, platform extension or running other lines at 4tph. This is not to mention that punctuality will be compromised, as each train will have to arrive at Bayswater at the exact scheduled time, or else trains after that one will be delayed.trains running even 45 seconds late may result in delays and reduction in capacity. The Midland Line will have to be quadruplicated up to Bayswater.

You could run the NCL right through to the SCL, instead of running to the city on the Midland Line. This would remove 2 lines from the Perth to Bayswater pinch point, cutting the number of lines there to 3. Each may run every 9 minutes (6 2/3 tph)on current signalling, or every 6 minutes (10 tph) with an upgrade, or double the figure with quadruplication. A new interchange station where the Midland Line intersects Tonkin Hwy would have to be built though, and airport trains would bypass this stop. SCL passengers will be able to have a zero walking distance transfer by changing to the airport line at an airport station, where both the SCL and Airport Line will call into the same platforms. There may be an extra charge on airport trains though, like in Sydney and Brisbane, which may be only be checked at entrances or enforced on board airport trains too. In addtion, reducing the number of lines does not change the fact that a large number of passengers will converge on the Midland Line between Perth and Bayswater.

LOCATION

Also an issue is the location of the NCL and SCL; the former in a highway median, the latter in primarily industrial lands.
We've yet to develop a good TOD at any of our existing freeway stations (Cockburn Central is alright, but cut off from the main commercial area (Gateway SC) by heavy traffic and car-oriented development along Beeliar Dr, as it is used to access the Kwinana Fwy), and for good reason - car traffic and pollution do not make good real estate marketing points, and the extensive park n' rides that follow car dependence do not make for quick and pleasant walks to the station. While there may be creative solutions, it is much simpler to build TODs outside of freeways. In some cases, non-highway TODs could harness suburb names that are already better than many highway-side suburbs (without naming anywhere).
As for industrial areas on the SCL, this is better, as there is no big, hulking highway to separate suburbs from their eponymous stations, but suburbs will still have to be radically different from what they are now. While it is good to serve industrial areas and their large employee numbers (as mentioned before, Kewdale is the area with the largest number of jobs out side of the inner city), industrial areas are typically large-scale and car/truck-dependent, and this must be changed if train lines serving such areas are to be well used. To kick out industry for residential and commercial development in response to this problem is also an issue; industrial areas cannot be simply pushed further and further out. The continued need for freight rail without delays to passenger trains will require wide rail corridors, without corresponding two-tier operation, frequency or existing urbanity.

COST

The costing of Metronet has been quite a contentious issue. First there was the Labour costing of $3.8 billion, then the $6.4 Liberal costing, and the Treasury costing sits in between at $4.335 billion ($5.2 billion by the time the project is finished). Let's see for ourselves what the plan might cost, in my mini - costing.

To be generous, I've thrown in a few extras, such as the aforementioned quadruplication to Bayswaters, and 4 km of tunnel for the airport section (the lack of this attacked by the Liberals in radio ads)

NCL - 17 km of surface rail
SCL - 42 km of surface rail (mostly amplified over the existing freight line, but new infrastructure is needed for passenger trains), 5 km of underground rail
Ellenbrook - 11km of surface rail
Butler to Yanchep (Clarkson to Butler is already under construction) - 13 km of surface rail
Armadale to Byford - 8 km of surface rail
Perth to Bayswater - 8 km of amplified surface track
Total - 91 km of surface rail, 5 km of underground rail, 8 km of amplified track

Approximate costs (using statistics from Martin 2010)
Surface rail - $20 million per km
Underground rail - $221.5 million per km
Track Quadruplication - $27.25 million per km

To try to account for inflation (I don't know how to do it properly), and also be conservative, I will add to these figures.
Surface rail - $25 million per km
Underground rail - $250 million per km
Track quadruplication - $30 million per km

The cost of Metronet should therefore come to -
$25 x 92 + $250 x 5 + 30 x 8 (mil)
= $2275 + $1250 + $240 (mil)
= $3769 (mil)
= $3.769 billion
Let's round that up to $3.8 billion

So even with a couple extras of my own, we come up with a costing less than anyone else's, but close to Labor's (which does not include quadding) Perhaps this is accounted for by the extra promises, such as the 17 000 extra parking spaces, the Circle Freeway or 144 new trains. Even so, the quoted costs did not include my extras, which were quite expensive. We really need public transport, so we need to make sure that money spent on it yields the greatest gains possible, by controlling our cost. What happened to our experience with the Mandurah Line, which despite its complexity, was one of the cheapest heavy rail projects in Australia of its time.

UPDATE: In line with my Liberals post, I've added an extra kilometre of tunnel, and taken that corresponding section from the surface rail part of the equation. My costing has been changed to reflect this.


Saturday, 2 February 2013

3/2/13 Service Changes (Western)

Map of Cambridge St changes.
Tomorrow there will be several major changes occurring to buses in the Western area.

The service along the Cambridge St corridor will be massively revamped. The 81, 84, 91 and 92 will all undergo time changes, and some of the above will be renumbered, with a new route introduced.

The 81 will see 3 extra morning peak services. The 6:10am departure from City Beach will be replaced with 6:00 and 6:20 buses, the 6:45am trip will be split into 6:40 and 6:55 journeys, and the 7:25 am service will become 7:20 and 7:35 buses.

The 84 will be renumbered to route 82, but it will still take the same route. There will be an earlier first bus, leaving City Beach at 6:05 am. There will also be an additional peak hour service, with 7:45 am departure replaced by 7:40 and 7:55 buses, and an extra evening service, leaving ther terminus usually only served by the 81 at 7:35 pm.

The 91 will be renumbered to 83, but again, no change to the routing. There will be extra morning trips, departing at 6:10 am and 6:35 am, and the peak hour 7:50 am service split into 7:40 am (replacing a service that currently commences and Grantham/Marlow Sts) and 7:55am trips, and the 8:20 am trip split into 8:10 and 8:30 trips.

The 92 will not be renumbered, becoming the odd one out of Cambridge St routes (presumably because the logical route number, 84, would be confusing if used for the 92, as it would only just have been used on a different route.

The new route 85 will also be introduced, replacing the 401. The 85 departs Wellington St Bus Stn and follows the other Cambridge St routes, until it turns off at Selby St, taking Flynn St, Reserve St, Herdsman Pde, Jon Sanders Dr, Harborne St and Scarborough Beach Rd to Glendalough Train Station. The first trip from Glendalough will be at 5:44 am, and the last trip leaving Wellington St will be at 6:30 pm on weekdays (the first and last trips on Saturdays are 6:54 am and 7pm). It will run every 20 minutes during peak hour, half-hourly on weekday middays and hourly on Saturdays.

Cambridge St will become a better frequent service corridor, with frequencies up to 19 bph (buses coming every 3 minutes and 9 sec on average) in the morning peak, 15 bph (4 minutely buses) in the afternoon peak,  every 10 minutes on weekday middays, every 15 to 25 minutes on Saturdays (a 15-20-25 cycle; I don't know why they haven't made it an even 20 minute frequency), and every 30 minutes on Sundays, along Cambridge St until Harborne St. There will also service every 5 to 12 minutes on Grantham St, and every 5 to 10 minutes along Cambridge St (to Selby ST in both cases) during the peaks.

Altogether, buses in the western suburbs will be immensely improved, but this is partially funded by the reduction of the 381 to one trip each way, as I commented previously. It could've made a good beach exploring routes, but would've needed to run on weekends and at a reasonable frequency. There's also the the deletion the 401. Daglish St, Ruislip, Vincent St and Bulwer St will no longer be served, but that isn't too great a loss, and those areas can be served in the future by a more useful and less convoluted bus route.

The other major change happening to Western bus services is that the 23, 78, 79, 102 and 107 will no longer serve Wellington St Stn; they will commence and terminate at Esplanade Busport. This is temporary, according to Transperth, because extra congestion due to construction would blow out running time between Wellington St Stn and Esplanade Busport, and the 30, 31, 34, 881 and 940 will still offer connections between the above two bus stations. That is understandable  but inconveniences travelers to UWA (or QEII Medical Centre, in the case of the 79), who come from across the metropolitan areas. To terminate the 30, 31, 34, 881 and 940 in the Busport and run the 23, 78, 79, 102 and 107 through to Wellington St would be much less inconvenient. Also, no extra time has been added to the routes that continue to go to Wellington St, to compensate for any construction. (These two concerns could be accounted for by the fact that only Swan Transit raised concerns over potential running times, except that Swan also operates the 34, and in any case, Transperth should communicate with other operators)

Sunday, 27 January 2013

3/2/13 Service Changes (Southern)

This post will detail the service changes to the Southern area occuring on 3rd February.

The 514, 515, 516, 520, 525, 526, 530, 531, 532, 543, 551, 552, 558, 559, 561, 584, 592, 594 and 600 will have time changes.

The 514 will have time changes, and the last Sunday trip from Murdoch (which left at 10:22 pm and did not have a corresponding trip from Murdoch prior to it) will be cut. It's a shame PT finishes early on Sundays, but there are trunk routes that don't have this service, so an hourly feeder finishing before 9:30pm isn't very important.
The 515 will have time changes, and more weekday services deviating to Jandakot Airport, and also more counter peak services (from Murdoch in the morning and to Murdoch in the afternoon, this is a very cheap enhancement, as the buses already ran something similar to that service, just not revenue service). I don't really understand the rationale behind running the 515 every 2 hours in the middle of the day. Yes, it may be a low-ridership route, but when a round trip on the 515 takes an hour, and there are no other buses running every 2 hours at Murdoch, so the bus doesn't do anythging for an hour and it would be very cheap to increase service to an hourly frequency(similar to the 251 on Sundays I talked about in the previous post).
The 516 will have time changes and a new deviation to Jandakot Airport every weekday morning, on the 7:43 bus from Murdoch (there's no corresponding return service, so I'm not sure what this is for. Those who take the bus in the morning but get lifts to the station in the afternoon?).

The 520, 530, 531 and 532 will begin to deviate to Cockburn Gateway Shopping City on Sundays because of Sunday trading, where previously they hadn't. The 531 will also deviate to Phoenix Shopping Centre.

The 564 will run two additional short services. One leaves its Baldivis terminus (Smirk Rd/Regency Av) at 7:30 am and concludes in Warnbro at 7:50am, and the other leaves Warnbro at 3:16pm arriving in Bladivis at 3:34pm. There will also be extra 568s, one leaving Warnbro at 7:56am, and terminating at Baldivis Secondary College, the other departing Nairn Dr/Kingaroy Dr at 8:17 am and deviating via Stocklands Baldivis SC, arriving at Warnbro at 8:39 am on school holidays, and 8:46am on schooldays due to a deviation to Baldivis Secondary College (Transperth sneakily refers to 'three additional weekdays services' on the 568, but in practice there are two services, just one that varies depending on whether school is in).

The 592 will have a route change. The bus will turn off Dawesville Bypass (when approaching from Mandurah) earlier, at Ocean Dr rather than Bailey Blvd, and use the new Dandaragan Dr to better serve new developments in Dawesville West.




Monday, 21 January 2013

3/2/13 Service Changes (South Eastern)

This post, second in a number of posts describing the service changes occurring across the Transperth network, concentrates on the South-Eastern service area.

The most significant change here is to services heading south of Armadale, to Byford, Mundijong, Jarrahdale and other areas. The 251 will have extra trips and the 251, 252 and 253 will have time changes and will be routed further down South Western Hwy to serve the Byford by the Scarp development better, and the new 254 will be introduced.
The 254 will serve the new developments in Byford, to the west of the railway line. It operates along a temporary route, since the new road network in that area is incomplete, and is fully accessible. It runs Monday to Saturday, every 15 minutes during the peaks and hourly at other times.
The 251, 252, 253 and 254 will interline from Armadale along South Western Hwy until Larsen Rd for a 30 minute frequency during weekday middays and on Saturdays (during peak hour, the 254 alone will run every 15 minutes, as stated above). Unfortunately, Sundays will see the lone 251 running every 2 hours, a far cry from the half-hourly service on weekdays. I don't see why this happens given one bus on a Sunday can run both the 250 and the 251, but not the 245 as well (all run every 2 hours). You can run the 250 and the 251 hourly on Sundays and still only use one bus. This means that running the bus every 2 hours saves no money on labour (there are small savings on maintenance due to less wear and tear, but a pittance compared to the potential doubling of frequencies).

There are also minor time changes to the 100, 101, 210, 211, 212, 229, 506, 507, 508 and 509, as well as an extra 212 trip leaving the Busport at 4:30pm, and numerous extra 100s and 101s, such as an earlier first trip on weekdays, leaving Curtin University as 5:50am, and an increase in frequency of buses between Curtin Uni and Canning Bridge in the mornings from 12 buses per hour (bph) to 18 bph (these buses previously deadheaded back to Canning Bridge, as the frequency from Canning Bridge to Curtin University was and stays at 18bph).

Tuesday, 15 January 2013

3/2/13 Service Changes (Eastern and Northern)

On 3rd February 2013 a whole wad of service changes will be implemented, across the Transperth network. This post will detail the changes occurring in the Eastern and Northern areas.

In the Eastern area, there will be a couple of extra trips on the 955 and 956 to Ellenbrook. There will be an extra 956 to Bassendean before the current first bus, leaving the terminus at 4:55am and arriving in Bassendean at 5:30am, improving the span of service, allowing passengers to arrive into the city before 6am, although it's a bit premature, I think, seeing as there are no buses for travellers to Ellenbrook leaving the city after 9:30pm. There is also an additional 955 to Ellenbrook, leaving Morley at 6:38pm and arriving in the Ellenbrook terminus at 7:22pm. This is a good improvement to afternoon peak shoulder service, where ther previously was a 45 minute gap in outbound buses.

In the Northern area, there will be time changes to the 410, 412 (adding different schedules for a couple of outbound weekday morning runs depending on whether it's a school day or school holiday), 415, 441, 443, and 444. Trips will be added to the 15 and 442.
The 15 will see school day only runs departing Wellington St Stn at 8:05am and 8:10am, terminating at Oxford St near Scarborough Beach Rd at 8:27am and 8:32am respectively, and the former school day-only service departing Wellington St at 8:15am forming a full service through to Glendalough.
The 442 will have an extra trip from Warwick Stn, departing at 6:50am, and arriving at Whitfords at 7:19am, a good morning peak bonus for those living on the northern section the 442.

Monday, 19 November 2012

If I ran Transperth... Suggested Minimum Frequency Standards: v2


I previously made a post about minimum frequency standards, but I will revise them now.
IDEAL MINIMUM FREQUENCY STANDARDS
Definitions
MONDAY TO THURSDAY -
Early Morning - 4am to 5am
Daytime - 5am to 10pm (excluding peak)
Peak - 6am to 10 am and 3pm to 7pm
Evening - 10pm to 12 am
Night(after) - 12am to 4am
FRIDAY -
Early Morning - 4am to 5am
Daytime - 5am to 10pm (excluding peak)

Peak - 6am to 10 am and 3pm to 7pm
Evening - 10pm to 2 am
Night - 2am to 4am
SATURDAY -
Early Morning - 5am to 6am

Daytime - 6am to 8pm
Evening - 8pm to 2 am
Night - 2am to 5am
SUNDAY

Daytime - 6am to 8pm
Evening - 8pm to 12 am
Early Morning - 5am to 6am
Night - 2am to 5am




I will provide some examples of service standards. Most routes should fit into these, but some may need special standards.
BRONZE
Every 15 minutes during peak, 30 minutes during (the rest of the) daytime and  60 minutes during evenings and early mornings.
SILVER
Every 7.5 minutes during peak, 15 minutes during the daytime, 30 minutes during evenings and early mornings, and 60 minutes at night.
GOLD
Greater service than Silver.

 As a result, most areas will get TUAG (every 15 minutes or more)service during the peak, and main routes (along most main roads) will receive TUAG from 5am to 10pm, and some kind of service 24/7. This trunk service could be depended on, and would make it possible to live comfortably in many parts of Perth without a car.